St.
Augustine
— The following is a list of roadwork underway by FDOT that may impact traffic
in Putnam and St. Johns counties. Please note: No project work will occur from
December 24, 2011 through January 2, 2012 unless otherwise noted below.
Putnam
County
US
17 South from the weigh station to Yelvington Road: Daytime lane closures
from 8:30 a.m. to 4 p.m. Monday, December 19 through Thursday, December 22 for
ditch cleaning.
St.
Johns County
State
Road 13 from the Julington Creek Bridge to Roberts Road: Daytime lane closures
from 9 a.m. to 4 p.m. Monday, December 19 through Wednesday, December 21 for
cleaning bike lanes and turn lanes.
State
Road 16 from the Clay County line to San Marco Avenue: Daytime lane closures
Monday, December 19 through Thursday, December 22 while crews repaint the
roadway markings.
State
Road 207 at County Road 305: Possible
daytime lane closures Monday, December 19 through Friday, December 23 for delivery
of equipment and materials to construct a multi-use trail from the end of the
existing trail to Armstrong Road. Work will continue on this project the week
of December 26, but no lane closures will be permitted and no impacts to
traffic will occur as a result of project work.
State
Road A1A – Summer Haven Bridges (just north of Marineland): Daytime lane closures at
the south bridge from 7 a.m. to 6 p.m. Monday, December 19 through Friday,
December 23. Motorists should drive with caution through the construction area.
The speed limit in this area has been reduced to 40 mph.
State
Road A1A from the Vilano Bridge to 23rd Street: Daytime lane closures from
9 a.m. to 3 p.m. Monday, December 19 for cleaning bike lanes.
State
Road A1A from the Flagler County line to Avenida Menendez: Daytime lane closures Monday,
December 19 through Thursday, December 22 while crews repaint the roadway
markings, excluding the construction zone in Summer Haven.
US
1 from State Road 16 to the Duval County line: Daytime lane closures
Monday, December 19 through Thursday, December 22 while crews repaint the
roadway markings.
US
1 at the San Sebastian River Bridge from Saragossa Street to King Street: Possible nighttime lane
closures from 7:30 p.m. to 6 a.m. in both directions Monday, December 19,
through Friday, December 23. Work
will continue on this project the week of December 26, but no lane closures
will be permitted and no impacts to traffic will occur as a result of project
work.
US
1 at Vaill Point Road:
One northbound lane is closed as well as the entrance to Vaill Point Road from
US 1 while crews for St. Johns County replace a pipe on the east side of the
Moultrie Creek Bridge. These closures are expected to continue until
mid-January 2012. For more information, contact James Overton with the St.
Johns County Utility Department. Work will continue on this project during the
week of December 26, and one northbound lane on US 1 and the entrance to Vaill
Point Road will remain closed during this time.